The Romgaz power plant in Iernut to be completed in June 2022

by   CIJ News iDesk V
2021-05-05   15:00
/uploads/posts/61aa79a8c5f6aafedd48b8834f614b4a29fae09d/images/843635998.jpg

The Romgaz plant in Iernut could be ready only in the middle of next year, in the context in which the investment of EUR 269 million should have been completed in 2019, according to an announcement made by Vlad Sincă, chairman of the PNI Commission (National Investment Plan).

"Considering the fact that SNGN Romgaz could not have completed the Iernut project until the deadline of 30.06.2021 (project already delayed and previously extended), the Ministry of Energy requested a new extension of the deadline for the European Commission and commissioning of projects through PNI until 30.06.2022. The answer was a positive one ", said Sincă.