Gara de Nord is to be modernized
CFR Infrastructură signed the contract for the "Modernization/consolidation/rehabilitation of the Gara de Nord Bucharest railway station - phase I" last year.
The duration of the contract is 116 months, of which:
– 55 months of design and execution of works, respectively 9 months of design and 46 months of execution of works,
– 1 month for verification and approval for payment of the works and tests upon completion
– 60 months of warranty period.
The winning bid, submitted by the association of Romanian companies SC GDO MOV IMPEX SRL – SC OMEGA CERT SISTEM SRL, is worth RON 419.85 million, excluding VAT.
PHASE I of the MODERNIZATION program of the largest railway station in Romania – GARA DE NORTH BUCHAREST – includes the rehabilitation of the existing spaces in the three buildings of the building, where railway activity is carried out, services for the traveling public and commercial activities are provided.